1 00:00:15,259 --> 00:00:12,650 Saturn five quarterly film report number 2 00:00:21,620 --> 00:00:15,269 seven covers progress during the period 3 00:00:23,990 --> 00:00:21,630 June July and August 1964 work on the s 4 00:00:28,089 --> 00:00:24,000 1c stage by Boeing and Marshall 5 00:00:33,200 --> 00:00:30,740 preparation for structural testing of 6 00:00:35,810 --> 00:00:33,210 the s 1c test fuel tank was completed 7 00:00:38,690 --> 00:00:35,820 and full pressure hydrostatic testing 8 00:00:41,090 --> 00:00:38,700 was begun by Boeing August 4th at the 9 00:00:43,069 --> 00:00:41,100 Marshall Space Flight Center but was 10 00:00:45,889 --> 00:00:43,079 interrupted when discrepancies in the 11 00:00:47,840 --> 00:00:45,899 test setup were encountered repair and 12 00:00:50,299 --> 00:00:47,850 rework of the test gear are in progress 13 00:00:54,500 --> 00:00:50,309 and resumption of testing is scheduled 14 00:00:56,720 --> 00:00:54,510 for mid September installation of the 15 00:00:59,810 --> 00:00:56,730 five locks tunnels on the fuel tank of 16 00:01:03,250 --> 00:00:59,820 the s 1 C T static firing stage was 17 00:01:06,410 --> 00:01:03,260 completed at Marshall on June 6th 18 00:01:09,649 --> 00:01:06,420 hydrostatic calibration and leak testing 19 00:01:14,870 --> 00:01:09,659 of the fuel tank began June 22nd and was 20 00:01:17,510 --> 00:01:14,880 completed July 20th on June 15th the S 1 21 00:01:17,980 --> 00:01:17,520 C T LOX tank half assemblies were welded 22 00:01:21,399 --> 00:01:17,990 together 23 00:01:23,359 --> 00:01:21,409 completing the LOX tank assembly 24 00:01:25,969 --> 00:01:23,369 hydrostatic testing of the LOX tank 25 00:01:28,550 --> 00:01:25,979 started August 6th and was successfully 26 00:01:32,929 --> 00:01:28,560 completed on August 15th with minor 27 00:01:35,569 --> 00:01:32,939 rework required installation of the heat 28 00:01:38,420 --> 00:01:35,579 shield for the s 1 CT thrust structure 29 00:01:39,950 --> 00:01:38,430 was started this quarter the framework 30 00:01:42,020 --> 00:01:39,960 of the shield was completed in August 31 00:01:43,580 --> 00:01:42,030 and was installed on the thrust 32 00:01:48,200 --> 00:01:43,590 structure with panel installation 33 00:01:50,600 --> 00:01:48,210 scheduled for next quarter cylindrical 34 00:01:52,969 --> 00:01:50,610 skin assembly and bulkhead fabrication 35 00:01:57,580 --> 00:01:52,979 work continued on the fuel tank for the 36 00:01:59,899 --> 00:01:57,590 s 1 C s structural test components 37 00:02:01,789 --> 00:01:59,909 assembly of components principally 38 00:02:04,490 --> 00:02:01,799 bulkheads or segments for the first 39 00:02:09,320 --> 00:02:04,500 flight stage s 1 C 1 got underway in 40 00:02:11,650 --> 00:02:09,330 June the S 1 C stage simulator has been 41 00:02:13,730 --> 00:02:11,660 cut into the forward and aft sections 42 00:02:15,290 --> 00:02:13,740 representing the LOX tank ascend 43 00:02:18,140 --> 00:02:15,300 li and the fuel tank assembly 44 00:02:20,360 --> 00:02:18,150 respectively and will be used next 45 00:02:22,580 --> 00:02:20,370 quarter in practice mating operations on 46 00:02:26,260 --> 00:02:22,590 the new horizontal assembly fixture 47 00:02:29,210 --> 00:02:26,270 scheduled for installation in September 48 00:02:31,280 --> 00:02:29,220 construction of Marshalls s1c static 49 00:02:33,770 --> 00:02:31,290 test stand is nearing completion with 50 00:02:37,310 --> 00:02:33,780 beneficial occupancy granted August 51 00:02:39,470 --> 00:02:37,320 first instrumentation equipment is now 52 00:02:41,390 --> 00:02:39,480 being installed in the control rooms of 53 00:02:45,230 --> 00:02:41,400 the block house which will serve both 54 00:02:48,850 --> 00:02:45,240 the s1c and the f1 engine static test 55 00:02:52,100 --> 00:02:48,860 stands at Marshalls mushy operations 56 00:02:54,650 --> 00:02:52,110 Boeing's first s1c production bulkhead 57 00:02:56,240 --> 00:02:54,660 neared completion it will be used on the 58 00:02:58,670 --> 00:02:56,250 locks tank of the structural test 59 00:03:02,210 --> 00:02:58,680 components vehicle being assembled at 60 00:03:04,240 --> 00:03:02,220 Marshall by the end of June Gore to Gore 61 00:03:06,800 --> 00:03:04,250 welding had been completed and 62 00:03:10,850 --> 00:03:06,810 instrumentation bracket spot welded into 63 00:03:13,040 --> 00:03:10,860 position bulkhead to Y ring trim and 64 00:03:15,260 --> 00:03:13,050 weld were accomplished during July and 65 00:03:19,730 --> 00:03:15,270 the unit was made ready for polar cap 66 00:03:22,850 --> 00:03:19,740 installation also at Massu Boeing 67 00:03:24,950 --> 00:03:22,860 assembled the first s-1 CD fuel tank 68 00:03:28,370 --> 00:03:24,960 ring by welding together its four 69 00:03:30,620 --> 00:03:28,380 sections and the ring was placed on this 70 00:03:35,750 --> 00:03:30,630 fixture for a D slash ring baffle 71 00:03:37,970 --> 00:03:35,760 installation Boeing s1 C component 72 00:03:41,390 --> 00:03:37,980 fabrication this quarter included 73 00:03:46,040 --> 00:03:41,400 emergency drain ducts for s1 c LOX and 74 00:03:53,930 --> 00:03:46,050 fuel tanks and LOX tank cylindrical skin 75 00:03:55,850 --> 00:03:53,940 panels at the seal Beach facility of 76 00:03:58,760 --> 00:03:55,860 North American Aviation space & 77 00:04:00,710 --> 00:03:58,770 Information Systems Division s2 stage 78 00:04:04,910 --> 00:04:00,720 manufacturing activities progressed 79 00:04:07,850 --> 00:04:04,920 steadily this quarter in June the s2 s 80 00:04:10,040 --> 00:04:07,860 structural test stage common bulkhead 81 00:04:13,010 --> 00:04:10,050 forward-facing sheet was installed on a 82 00:04:16,190 --> 00:04:13,020 tracing fixture and a vacuum Bell was 83 00:04:18,410 --> 00:04:16,200 installed over the facing sheet a vacuum 84 00:04:21,140 --> 00:04:18,420 was applied to draw the facing sheet to 85 00:04:23,060 --> 00:04:21,150 a smooth contour and the inner surface 86 00:04:25,580 --> 00:04:23,070 of the facing sheet was traced or 87 00:04:26,610 --> 00:04:25,590 measured the vacuum Bell was then 88 00:04:29,909 --> 00:04:26,620 removed 89 00:04:31,650 --> 00:04:29,919 based on the tracing data machining of 90 00:04:33,480 --> 00:04:31,660 the surface of the honeycomb core 91 00:04:37,980 --> 00:04:33,490 covered aft facing sheet was 92 00:04:40,290 --> 00:04:37,990 accomplished on July 30th a major 93 00:04:43,409 --> 00:04:40,300 milestone was reached when the final 94 00:04:46,110 --> 00:04:43,419 bond on the s2 s common bulkhead was 95 00:04:47,659 --> 00:04:46,120 completed before bonding to impression 96 00:04:50,280 --> 00:04:47,669 checks were made 97 00:04:53,010 --> 00:04:50,290 polyvinyl coating was applied over the 98 00:04:55,379 --> 00:04:53,020 honeycomb area the forward-facing sheet 99 00:04:58,140 --> 00:04:55,389 supported by the vacuum bail was lowered 100 00:05:00,800 --> 00:04:58,150 onto the assembly and a vacuum was 101 00:05:03,360 --> 00:05:00,810 applied between the two facing sheets 102 00:05:05,760 --> 00:05:03,370 prior to applying adhesive to the 103 00:05:08,070 --> 00:05:05,770 forward facing sheet vacuum was applied 104 00:05:10,650 --> 00:05:08,080 between the vacuum bail and the forward 105 00:05:15,120 --> 00:05:10,660 facing sheet in order to remove caning 106 00:05:16,620 --> 00:05:15,130 or indentations a TCO film was applied 107 00:05:19,080 --> 00:05:16,630 to the inner surface of the 108 00:05:21,900 --> 00:05:19,090 forward-facing sheet after cleaning and 109 00:05:24,379 --> 00:05:21,910 priming supported by the vacuum Bell it 110 00:05:27,629 --> 00:05:24,389 was lowered under the honeycomb core 111 00:05:30,270 --> 00:05:27,639 after fitting and applying a vacuum 112 00:05:32,760 --> 00:05:30,280 between facing sheets the vacuum bail 113 00:05:35,430 --> 00:05:32,770 was removed and the assembly placed in 114 00:05:38,540 --> 00:05:35,440 the autoclave for the bonding cycle to 115 00:05:40,830 --> 00:05:38,550 produce the first s2 common bulkhead 116 00:05:43,430 --> 00:05:40,840 welding of this bulkhead to cylinder 117 00:05:46,050 --> 00:05:43,440 number one and two sub assembly and 118 00:05:50,400 --> 00:05:46,060 hydrostatic testing of this unit will be 119 00:05:53,520 --> 00:05:50,410 accomplished next quarter the s2 s3 120 00:05:55,620 --> 00:05:53,530 structure and aft skirt assembly was 121 00:05:57,510 --> 00:05:55,630 transferred to station number three of 122 00:06:00,270 --> 00:05:57,520 the vertical Assembly Building in June 123 00:06:03,120 --> 00:06:00,280 and waiting to the static firing skirt 124 00:06:05,370 --> 00:06:03,130 was accomplished the liquid hydrogen 125 00:06:07,770 --> 00:06:05,380 forward bulkhead and liquid hydrogen 126 00:06:11,100 --> 00:06:07,780 tank cylinder number six assembly for 127 00:06:12,779 --> 00:06:11,110 the s2 s was moved out of station two 128 00:06:15,750 --> 00:06:12,789 in the vertical Assembly Building in 129 00:06:17,909 --> 00:06:15,760 early June and installed in station six 130 00:06:20,540 --> 00:06:17,919 where hydrostatic testing of the 131 00:06:23,159 --> 00:06:20,550 assembly was successfully performed 132 00:06:25,409 --> 00:06:23,169 following hydrostatic testing the mating 133 00:06:28,560 --> 00:06:25,419 of this assembly to the s2 s forward 134 00:06:30,690 --> 00:06:28,570 skirt was accomplished in July to attach 135 00:06:32,760 --> 00:06:30,700 the skirt a total of five hundred 136 00:06:37,980 --> 00:06:32,770 seventy two mating holes were located 137 00:06:40,050 --> 00:06:37,990 and drilled also during the quarter the 138 00:06:42,060 --> 00:06:40,060 insulated lh2 quarter 139 00:06:44,220 --> 00:06:42,070 paddles for the common bulkhead test 140 00:06:47,010 --> 00:06:44,230 tank were ultrasonically inspected for 141 00:06:50,640 --> 00:06:47,020 bonding deficiencies with all panels 142 00:06:52,740 --> 00:06:50,650 proving satisfactory at the s and ID 143 00:06:55,800 --> 00:06:52,750 cryogenic test facility at Downey 144 00:06:58,920 --> 00:06:55,810 California development qualification 145 00:07:02,070 --> 00:06:58,930 testing of the 1.6 inch thick helium 146 00:07:06,120 --> 00:07:02,080 purged foam filled insulation design for 147 00:07:07,909 --> 00:07:06,130 the s2 1 2 & 3 was successfully 148 00:07:10,820 --> 00:07:07,919 performed in July 149 00:07:13,650 --> 00:07:10,830 major sub assembly on the s2 f 150 00:07:15,570 --> 00:07:13,660 facilities checkout stage started in 151 00:07:18,629 --> 00:07:15,580 late June with the installation of a 152 00:07:23,280 --> 00:07:18,639 Gore segment on the common bulkhead aft 153 00:07:25,590 --> 00:07:23,290 facing sheet Meridian weld fixture at 154 00:07:28,080 --> 00:07:25,600 the Santa Susana static test facility 155 00:07:31,920 --> 00:07:28,090 activation of the s2 Battleship tests 156 00:07:34,290 --> 00:07:31,930 and continued on July 29th demonstration 157 00:07:41,610 --> 00:07:34,300 of the flame deflector water system was 158 00:07:43,290 --> 00:07:41,620 successfully accomplished at Douglas 159 00:07:46,020 --> 00:07:43,300 Aircraft company's Huntington Beach 160 00:07:48,330 --> 00:07:46,030 facility additional instrumentation was 161 00:07:50,790 --> 00:07:48,340 installed on the s4 be hydrostatic 162 00:07:52,980 --> 00:07:50,800 vehicle early this quarter at Marshall 163 00:07:55,820 --> 00:07:52,990 Center direction in order to provide 164 00:07:59,969 --> 00:07:55,830 more complete data an event of a rupture 165 00:08:02,279 --> 00:07:59,979 on July 14th structural damage occurred 166 00:08:05,610 --> 00:08:02,289 on the hydrostatic vehicle due to a weld 167 00:08:09,900 --> 00:08:05,620 failure during hydrostatic testing the 168 00:08:12,659 --> 00:08:09,910 rupture occurred at 34 psi g2 psig less 169 00:08:14,700 --> 00:08:12,669 than proof pressure the liquid hydrogen 170 00:08:17,100 --> 00:08:14,710 tank could not be salvaged 171 00:08:19,409 --> 00:08:17,110 but the LOX tank common bulkhead will be 172 00:08:21,300 --> 00:08:19,419 repaired and the LOX tank used in 173 00:08:24,629 --> 00:08:21,310 connection with structural testing of 174 00:08:27,270 --> 00:08:24,639 the thrust structure by reduction and 175 00:08:29,580 --> 00:08:27,280 analysis of test data obtained prior to 176 00:08:31,200 --> 00:08:29,590 rupture of the hydrostatic tank it was 177 00:08:33,540 --> 00:08:31,210 determined that it will not be necessary 178 00:08:37,769 --> 00:08:33,550 to resume hydrostatic testing on a 179 00:08:39,860 --> 00:08:37,779 future structural vehicle the s4 be 180 00:08:42,510 --> 00:08:39,870 dynamic vehicle was moved into 181 00:08:45,810 --> 00:08:42,520 insulation chamber number one in early 182 00:08:49,829 --> 00:08:45,820 June and insulation was installed by a 183 00:08:52,050 --> 00:08:49,839 mid July the all system stage tank 184 00:08:54,269 --> 00:08:52,060 assembly has been completed 185 00:08:58,230 --> 00:08:54,279 has been prepared for installation of 186 00:09:00,000 --> 00:08:58,240 cryogenic insulation assembly of the 187 00:09:03,750 --> 00:09:00,010 facilities checkout vehicle was 188 00:09:06,540 --> 00:09:03,760 completed in late August at Douglass's 189 00:09:10,079 --> 00:09:06,550 Sacramento test area work continued on 190 00:09:13,800 --> 00:09:10,089 the beta and gamma facilities in June 191 00:09:16,620 --> 00:09:13,810 the j2 engine was installed on the s4 be 192 00:09:19,110 --> 00:09:16,630 battleship tank as the report period 193 00:09:21,990 --> 00:09:19,120 ended preparations were being made for 194 00:09:25,079 --> 00:09:22,000 cold flow and hot firing tests next 195 00:09:27,000 --> 00:09:25,089 quarter checkout of battleship ground 196 00:09:31,200 --> 00:09:27,010 support equipment continued at the beta 197 00:09:33,720 --> 00:09:31,210 block house at the Gama facility the 198 00:09:36,060 --> 00:09:33,730 attitude control engines for the s4 be 199 00:09:39,300 --> 00:09:36,070 auxilary propulsion system were received 200 00:09:41,340 --> 00:09:39,310 from TEPCO in Los Angeles the engines 201 00:09:49,590 --> 00:09:41,350 are being installed and testing will 202 00:09:52,079 --> 00:09:49,600 start next quarter engine number 12:1 203 00:09:54,269 --> 00:09:52,089 this quarter became the first f1 engine 204 00:09:56,760 --> 00:09:54,279 to be equipped with the new rigid 205 00:09:58,590 --> 00:09:56,770 high-pressure propellant lines these 206 00:10:01,380 --> 00:09:58,600 offers several advantages over the 207 00:10:04,350 --> 00:10:01,390 former design being lighter more easily 208 00:10:06,870 --> 00:10:04,360 fabricated and providing a reduction in 209 00:10:09,480 --> 00:10:06,880 pressure drop by eliminating internal 210 00:10:12,030 --> 00:10:09,490 restrictions to reduce turbine back 211 00:10:13,800 --> 00:10:12,040 pressure a new turbine exhaust manifold 212 00:10:16,470 --> 00:10:13,810 Inlet has been designed and fabricated 213 00:10:18,900 --> 00:10:16,480 by Rocketdyne this configuration 214 00:10:21,120 --> 00:10:18,910 provides improved flow and pressure 215 00:10:24,960 --> 00:10:21,130 distribution to the manifold and nozzle 216 00:10:27,690 --> 00:10:24,970 extension the first block to heat 217 00:10:30,750 --> 00:10:27,700 exchanger has been received and will 218 00:10:33,180 --> 00:10:30,760 soon undergo testing the new unit has a 219 00:10:35,100 --> 00:10:33,190 shell configuration which eliminates the 220 00:10:39,660 --> 00:10:35,110 shroud formerly used while maintaining 221 00:10:43,560 --> 00:10:39,670 the required gas flow of velocity the f1 222 00:10:46,650 --> 00:10:43,570 engine o84 d-type injector is now 223 00:10:49,019 --> 00:10:46,660 undergoing development test this 224 00:10:51,300 --> 00:10:49,029 injector design appears to meet the 225 00:10:54,780 --> 00:10:51,310 flight rating test specific impulse and 226 00:10:57,420 --> 00:10:54,790 other required characteristics at the 227 00:11:00,030 --> 00:10:57,430 Edwards rocket engine test site f1 228 00:11:01,489 --> 00:11:00,040 engine tests and number one D was 229 00:11:04,460 --> 00:11:01,499 activated 230 00:11:06,739 --> 00:11:04,470 this is the first of three new stands 231 00:11:19,189 --> 00:11:06,749 which will be used for production engine 232 00:11:21,679 --> 00:11:19,199 acceptance testing at the Marshall 233 00:11:25,129 --> 00:11:21,689 Center propulsion testing on the second 234 00:11:27,859 --> 00:11:25,139 f1 production engine began on June 23rd 235 00:11:30,499 --> 00:11:27,869 and continued during the quarter in the 236 00:11:33,079 --> 00:11:30,509 modified s1 stage test and which 237 00:11:36,259 --> 00:11:33,089 includes a simulation of s1 sea tank 238 00:11:38,119 --> 00:11:36,269 each and ducting propulsion testing of 239 00:11:42,499 --> 00:11:38,129 the first production engine began last 240 00:11:44,780 --> 00:11:42,509 quarter also continued construction of 241 00:11:47,210 --> 00:11:44,790 the f1 engine static test and at 242 00:11:49,129 --> 00:11:47,220 Marshall is now virtually complete with 243 00:11:53,419 --> 00:11:49,139 beneficial occupancy scheduled in 244 00:11:55,699 --> 00:11:53,429 September water flow check out of the 245 00:12:00,109 --> 00:11:55,709 stands deflector plate was performed on 246 00:12:02,989 --> 00:12:00,119 August 20th maximum flow is 136 thousand 247 00:12:04,970 --> 00:12:02,999 gallons per minute the first f1 engine 248 00:12:09,470 --> 00:12:04,980 firing on the new stand is set for 249 00:12:12,230 --> 00:12:09,480 mid-november at Marshalls f1 turbo pump 250 00:12:15,079 --> 00:12:12,240 facility build-up and activation are in 251 00:12:17,929 --> 00:12:15,089 the final phases and checkout has begun 252 00:12:20,780 --> 00:12:17,939 the facility will provide a simulation 253 00:12:23,449 --> 00:12:20,790 of vehicle net positive suction head for 254 00:12:28,220 --> 00:12:23,459 both fuel and locks for turbo pump 255 00:12:30,590 --> 00:12:28,230 testing culminating a series of 256 00:12:33,739 --> 00:12:30,600 successful gimbal intest begun last 257 00:12:35,419 --> 00:12:33,749 order the Rocketdyne j2 engine has 258 00:12:37,280 --> 00:12:35,429 demonstrated its ability to meet 259 00:12:39,199 --> 00:12:37,290 preliminary flight rating test 260 00:12:43,309 --> 00:12:39,209 requirements for gambling during hot 261 00:12:45,679 --> 00:12:43,319 firing this latest model gimbal assembly 262 00:12:48,199 --> 00:12:45,689 has gambled the j2 system in tests at 263 00:12:52,489 --> 00:12:48,209 the rate of 30 degrees per second to a 264 00:12:55,189 --> 00:12:52,499 maximum of 10 degrees an initial 265 00:12:57,739 --> 00:12:55,199 altitude testing of the spark plug of 266 00:13:00,079 --> 00:12:57,749 the j2 engines augmented spark ignition 267 00:13:02,030 --> 00:13:00,089 system the plug was successfully 268 00:13:03,710 --> 00:13:02,040 operated in a vacuum environment to 269 00:13:06,859 --> 00:13:03,720 determine its characteristics in outer 270 00:13:09,319 --> 00:13:06,869 space a corona effect as apparent as the 271 00:13:13,639 --> 00:13:09,329 plug operates through a 100,000 to 272 00:13:14,240 --> 00:13:13,649 200,000 foot altitude range experimental 273 00:13:16,370 --> 00:13:14,250 studies 274 00:13:19,370 --> 00:13:16,380 to determine fuel flow uniformity of the 275 00:13:21,080 --> 00:13:19,380 j2 thrust chamber tubes were conducted 276 00:13:25,310 --> 00:13:21,090 by Rocketdyne this quarter in a high 277 00:13:27,500 --> 00:13:25,320 flow test chamber with 1125 to 2250 278 00:13:30,680 --> 00:13:27,510 gallons of water per minute being pumped 279 00:13:33,590 --> 00:13:30,690 through the chamber Rocketdyne assembly 280 00:13:35,540 --> 00:13:33,600 of flexible armored harnesses for all j2 281 00:13:37,310 --> 00:13:35,550 engine electrical control and 282 00:13:39,890 --> 00:13:37,320 instrumentation harness wiring is 283 00:13:42,230 --> 00:13:39,900 underway this will provide complete 284 00:13:44,960 --> 00:13:42,240 moisture protection handling and 285 00:13:47,690 --> 00:13:44,970 abrasion protection and short-term fire 286 00:13:51,080 --> 00:13:47,700 protection for the 14 individual harness 287 00:13:53,510 --> 00:13:51,090 assemblies in the j2 engine system at 288 00:13:56,330 --> 00:13:53,520 the Marshall Center construction of the 289 00:13:59,600 --> 00:13:56,340 j2 engine test facility is approximately 290 00:14:02,840 --> 00:13:59,610 85% complete with beneficial occupancy 291 00:14:05,690 --> 00:14:02,850 expected in November the facility will 292 00:14:08,270 --> 00:14:05,700 be used to static fire single hydrogen 293 00:14:11,060 --> 00:14:08,280 fueled engines with thrust ratings up to 294 00:14:18,950 --> 00:14:11,070 200 thousand pounds for test durations 295 00:14:21,440 --> 00:14:18,960 up to 500 seconds redesign of the Saturn 296 00:14:23,990 --> 00:14:21,450 5 instrument unit structure necessitated 297 00:14:26,810 --> 00:14:24,000 by revised vehicle loads was completed 298 00:14:28,610 --> 00:14:26,820 in August structural units such as the 299 00:14:31,430 --> 00:14:28,620 facilities checkout unit already 300 00:14:33,950 --> 00:14:31,440 delivered to the old design will be used 301 00:14:36,740 --> 00:14:33,960 for tests not involving structural 302 00:14:38,450 --> 00:14:36,750 testing delivery of the first new iu 303 00:14:40,700 --> 00:14:38,460 structure to Marshall is due next 304 00:14:41,560 --> 00:14:40,710 quarter from General Dynamics Fort Worth 305 00:14:45,260 --> 00:14:41,570 Texas 306 00:14:47,420 --> 00:14:45,270 at Marshall this quarter a prototype of 307 00:14:49,100 --> 00:14:47,430 the heat exchanger which will be used in 308 00:14:51,230 --> 00:14:49,110 the instrument unit environmental 309 00:14:54,350 --> 00:14:51,240 control system underwent successful 310 00:14:56,900 --> 00:14:54,360 testing the heat exchanger will provide 311 00:14:59,870 --> 00:14:56,910 temperature control for the IU equipment 312 00:15:03,590 --> 00:14:59,880 as well as for other instrumentation in 313 00:15:06,500 --> 00:15:03,600 the s4b stage just below by cooling a 314 00:15:08,450 --> 00:15:06,510 water methanol solution which circulates 315 00:15:10,550 --> 00:15:08,460 through the cold plates to which the 316 00:15:14,210 --> 00:15:10,560 various instrumentation devices are 317 00:15:17,690 --> 00:15:14,220 mounted around the eye you will be 318 00:15:20,110 --> 00:15:17,700 located 16 such cold plates one of which 319 00:15:23,230 --> 00:15:20,120 is depicted in this cutaway drawing 320 00:15:26,449 --> 00:15:23,240 similar panels will be used for the s4b 321 00:15:28,160 --> 00:15:26,459 instrumentation made of raised aluminum 322 00:15:30,560 --> 00:15:28,170 each panel is 30 323 00:15:34,340 --> 00:15:30,570 square and one in one quarter inches 324 00:15:36,230 --> 00:15:34,350 thick contract negotiations are still in 325 00:15:39,079 --> 00:15:36,240 progress with International Business 326 00:15:41,420 --> 00:15:39,089 Machines selected last quarter as prime 327 00:15:45,110 --> 00:15:41,430 contractor to take over development and 328 00:15:47,000 --> 00:15:45,120 fabrication of the IU meanwhile iBM has 329 00:15:49,040 --> 00:15:47,010 gone forward with its efforts in 330 00:15:57,889 --> 00:15:49,050 facilities and personnel build-up at 331 00:16:00,379 --> 00:15:57,899 Huntsville prototype ground support 332 00:16:02,740 --> 00:16:00,389 equipment for the s1c stage electrical 333 00:16:05,629 --> 00:16:02,750 and mechanical tests control stations 334 00:16:08,030 --> 00:16:05,639 underwent tests and check-out by Boeing 335 00:16:12,199 --> 00:16:08,040 at the Marshall Center during the report 336 00:16:14,360 --> 00:16:12,209 period ground support equipment systems 337 00:16:17,180 --> 00:16:14,370 measuring device tests consoles and 338 00:16:19,220 --> 00:16:17,190 electrical harnesses for s2 stages were 339 00:16:21,590 --> 00:16:19,230 being assembled and checked out during 340 00:16:24,290 --> 00:16:21,600 the quarter at SN I DS Compton 341 00:16:26,480 --> 00:16:24,300 California facility the remote power 342 00:16:29,780 --> 00:16:26,490 distribution rack the first major item 343 00:16:31,970 --> 00:16:29,790 of deliverable GSE was shipped to the 344 00:16:34,610 --> 00:16:31,980 Santa Susana static test facility on 345 00:16:37,970 --> 00:16:34,620 July 10th to support the Battleship test 346 00:16:39,800 --> 00:16:37,980 program at Douglas Aircraft company's 347 00:16:42,350 --> 00:16:39,810 Huntington Beach California systems 348 00:16:44,689 --> 00:16:42,360 integration laboratory checkout of the 349 00:16:48,410 --> 00:16:44,699 initial set of the s4b ground support 350 00:16:50,540 --> 00:16:48,420 equipment is nearing completion the 351 00:16:53,540 --> 00:16:50,550 systems integration lab vehicle 352 00:16:56,180 --> 00:16:53,550 simulator is also nearly finished the 353 00:16:58,430 --> 00:16:56,190 simulator which will include a j2 engine 354 00:17:02,180 --> 00:16:58,440 will be used to prepare checkout tapes 355 00:17:04,370 --> 00:17:02,190 for checkout of flight stages at 356 00:17:06,640 --> 00:17:04,380 Marshall Saturn five ground support 357 00:17:08,960 --> 00:17:06,650 equipment test facility brick-and-mortar 358 00:17:11,900 --> 00:17:08,970 construction is approximately 90% 359 00:17:13,610 --> 00:17:11,910 complete the control room has been 360 00:17:16,699 --> 00:17:13,620 finished with beneficial occupancy 361 00:17:18,439 --> 00:17:16,709 granted August 1st installation of 362 00:17:22,309 --> 00:17:18,449 technical systems is scheduled to begin 363 00:17:24,590 --> 00:17:22,319 in September testing of various ground 364 00:17:25,610 --> 00:17:24,600 support equipment such as this prototype 365 00:17:28,580 --> 00:17:25,620 s4b 366 00:17:30,169 --> 00:17:28,590 aft swing arm chip assembly is being 367 00:17:32,690 --> 00:17:30,179 conducted for the Kennedy Space Center 368 00:17:34,850 --> 00:17:32,700 in temporary facilities at Marshall 369 00:17:38,930 --> 00:17:34,860 while construction of the GSE test 370 00:17:41,520 --> 00:17:38,940 facility is underway this prototype s 1c 371 00:17:43,650 --> 00:17:41,530 tail service mast is another item 372 00:17:52,460 --> 00:17:43,660 tested at Marshall to prove the design 373 00:17:57,000 --> 00:17:54,720 construction work on the Saturn 5 374 00:17:59,880 --> 00:17:57,010 dynamic test and that the Marshall 375 00:18:02,570 --> 00:17:59,890 Center is now virtually finished with 376 00:18:05,640 --> 00:18:02,580 completion scheduled in September 377 00:18:07,680 --> 00:18:05,650 Marshalls 30 million pound capacity load 378 00:18:10,140 --> 00:18:07,690 test tower was practically completed 379 00:18:12,840 --> 00:18:10,150 this quarter with beneficial occupancy 380 00:18:14,820 --> 00:18:12,850 granted the last week in August initial 381 00:18:17,100 --> 00:18:14,830 use of the new facility for structural 382 00:18:20,820 --> 00:18:17,110 testing of an S 1 C inter tank is 383 00:18:22,830 --> 00:18:20,830 scheduled in September at Marshall 384 00:18:25,320 --> 00:18:22,840 Saturn five barge dock and loading 385 00:18:27,330 --> 00:18:25,330 facility on the Tennessee River dry 386 00:18:29,580 --> 00:18:27,340 excavation for the dock is complete 387 00:18:32,040 --> 00:18:29,590 pile-driving is about 90 percent 388 00:18:34,320 --> 00:18:32,050 finished and the concrete work and pier 389 00:18:37,130 --> 00:18:34,330 have been started overall construction 390 00:18:40,500 --> 00:18:37,140 is approximately forty percent complete 391 00:18:42,570 --> 00:18:40,510 at Marshalls Mississippi test facility 392 00:18:46,410 --> 00:18:42,580 construction continued this quarter at 393 00:18:48,900 --> 00:18:46,420 the three complexes at the test complex 394 00:18:51,320 --> 00:18:48,910 pouring of the foundation for the s1c 395 00:18:55,110 --> 00:18:51,330 dual position static test and is 396 00:18:58,500 --> 00:18:55,120 approximately 25 percent complete at the 397 00:19:01,730 --> 00:18:58,510 first s2 static test and foundation work 398 00:19:03,900 --> 00:19:01,740 is approximately 55 percent complete 399 00:19:06,750 --> 00:19:03,910 excavation has been completed at the 400 00:19:10,560 --> 00:19:06,760 second nest to stand and pile-driving is 401 00:19:12,810 --> 00:19:10,570 nearing completion at the laboratory and 402 00:19:14,310 --> 00:19:12,820 engineering complex construction 403 00:19:16,770 --> 00:19:14,320 continued on the office and 404 00:19:20,130 --> 00:19:16,780 administration building data handling 405 00:19:23,670 --> 00:19:20,140 Center and a telephone and terminal 406 00:19:26,100 --> 00:19:23,680 building and at the support services 407 00:19:28,230 --> 00:19:26,110 complex work progressed on such 408 00:19:32,220 --> 00:19:28,240 facilities as the emergency services 409 00:19:35,090 --> 00:19:32,230 building MTF warehouse site maintenance 410 00:19:39,540 --> 00:19:35,100 building central heating plant and 411 00:19:42,570 --> 00:19:39,550 electrical substation the design stage 412 00:19:44,960 --> 00:19:42,580 of the first phase of the MTF technical 413 00:19:46,680 --> 00:19:44,970 systems is essentially complete 414 00:19:48,920 --> 00:19:46,690 contracts have been awarded for 415 00:19:51,480 --> 00:19:48,930 procurement of cable trays 416 00:19:54,180 --> 00:19:51,490 instrumentation cables and control 417 00:19:55,379 --> 00:19:54,190 cables installation of the system is 418 00:19:59,399 --> 00:19:55,389 scheduled to begin 419 00:20:02,310 --> 00:19:59,409 this year work also progressed at 420 00:20:04,819 --> 00:20:02,320 Pascagoula Mississippi on modification 421 00:20:07,440 --> 00:20:04,829 of several government-owned barges and 422 00:20:10,259 --> 00:20:07,450 fitting them with barge tanks for 423 00:20:16,199 --> 00:20:10,269 transporting liquid cryogenics to be 424 00:20:18,869 --> 00:20:16,209 used at MTF in summary June July and 425 00:20:20,789 --> 00:20:18,879 August were months of substantial 426 00:20:24,479 --> 00:20:20,799 progress along a broad front of 427 00:20:27,810 --> 00:20:24,489 activities assembly of s1c stages gained 428 00:20:31,319 --> 00:20:27,820 momentum the first s to common bulkhead 429 00:20:34,409 --> 00:20:31,329 was completed s4b ground stage assembly 430 00:20:36,899 --> 00:20:34,419 continued and significant progress was 431 00:20:39,209 --> 00:20:36,909 achieved on the engine programs the